• You are here:
  • Home »

VMMC CCU and Oncology

PROJECT TITLE: VIRGINIA MASON JONES PAVILION CCU AND ONCOLOGY NURSING UNITS

VMMC had constructed the shell & core several years earlier.  Project included design of pre-fabricated restroom units with toilet, sink & shower, pre-fabricated mechanical frames and piping sections.  28 Critical Care Unit included a Radiology suite with CT Scan & X-ray unit.  The 24 bed Oncology Unit included a Pharmacy included ante-chamber and Infusion mixing hoods.  Full scale mock-ups constructed and simulations conducted on both floors.  Design was successful to segregate the flow of materials and supplies from the movement of patients and families.  Spaces were provided for both families and staff respite areas on each floor.  Pass-thru patient care supply cabinets were installed between the patient room and hallway to minimize the interruptions into the room that materials and EVS staff might otherwise make.   

LOCATION: SEATTLE, WA

PROJECT SIZE:  28,000 SF 28 bed Critical Care Unit & Radiology Suite, 24,000 SF 24 bed Oncology Unit and Infusion Pharmacy,

PROJECT COST: $21 Million CCU & Radiology, $19 Million Oncology & Pharmacy

STATUS:  Completed 2014

PROJECT TEAM:

TGB Architects

Skanska Construction

CPL Structural Engineers

Macdonald Miller

Veca Electric

OTHER: Zero external staging area mandated that much of the work was prefabricated, delivered to street side crane, and lifted into place through an existing window opening on the un-occupied floor. 

About the Author PFDeveloper